Hi Everyone… Could you help me with the following problem
After allocating a Resource to an Activity(Task Dependent), when i change my Resource Calendar, Budgeted Units are not changing accordingly.
For example, I’ve a Resource(with 8Hr Resource Calendar) which is allocated to an activity with Budgeted Units “1d or 8h” .Now, if i change my resource calendar to a 10 Hr Calendar, its not being reflected in the Budgeted Units.It still shows Budgeted Units as “8 Hrs”.I tried reallocating the resource, but it didn’t work.Why is it so?
If the Activity Calendar is changed, the Activity Durations would change according to the Time Period of the new Calendar.I was expecting the same to happen with Budgeted Units when the Resource Calendar was changed.
From this, what i conclude is for a Task Dependent Activity, Activity Calendar determines the conversion and for a Resource Dependent Activity, it’s the Resource Calendar that determines the conversion in Budgeted Units.Is my understanding correct?
Replies