Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Show activity dates in EPS view in EPPM

2 replies [Last post]
Chary Chary
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 6 Apr 2016
Posts: 15
Groups: None

Dear all,

I have a need to see dates of some of the milestones of a project in EPS view in EPPMIn general 

In general I can see, that some of the dates can be shown in EPS view:

e.g. :

Start / Finish

BL Start / BL finish

 

But what if I create a Milestone1 for every project and then want to see for every project

Milestone1 Start

BL Milestone1 Start

 

can this be done?

If not, what is the way to achieve this? (I assume it can be done, by making some SQL query)

 

 

Replies

Santosh Bhat
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

1) Use a Global Activity code or a UDF to flag all those milestones in each project.

2) Open all the projects - you can do this by opening an entire project node in projects view

3) Create a filter that selects only activities that have been flagged in 1) above

4) Group your activity layout to by EPS/WBS and tick the option Show Summaries Only

5) Use colours/fonts of the grouping bands to achieve the look you want and save this Activity layout.

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
You may use UDF.