Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Assignment

4 replies [Last post]
Mike planner
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hi All, 

 

Can i know why i can see the resource on each day? 

 

For example, i have 4000 unit assign to activity A1010 but i only can see 800. I have 5 days on that activity so it should be 800, 800, 800, 800, 800 

 

Thanks

Mike 

 

 

7167
1.png

Replies

Zoltan Palffy
User offline. Last seen 2 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if it a a LOE it will stack it on the 1st day unless you assign a curve to it

Raymund de Laza
User offline. Last seen 30 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Assign linear resource curve.

Mike planner
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hi, 

 

Thank you for the reply. i checked, it was set to Day. It doesnt show the resource on day on resource assignment tho

 

7170
1.png

 

Many thanks

Mike

Raymund de Laza
User offline. Last seen 30 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
Hi, set the resource analysis to daily in the user preferences.