Resource Assignment

4 replies [Last post]
Mike planner
User offline. Last seen 18 hours 41 min ago. Offline
Joined: 3 Feb 2011
Posts: 45
Groups: None

Hi All, 

 

Can i know why i can see the resource on each day? 

 

For example, i have 4000 unit assign to activity A1010 but i only can see 800. I have 5 days on that activity so it should be 800, 800, 800, 800, 800 

 

Thanks

Mike 

 

 

7167
1.png

Replies

Zoltan Palffy
User offline. Last seen 19 hours 13 min ago. Offline
Joined: 13 Jul 2009
Posts: 2716
Groups: None

if it a a LOE it will stack it on the 1st day unless you assign a curve to it

Raymund de Laza
User offline. Last seen 51 min 21 sec ago. Offline
Joined: 23 Nov 2009
Posts: 744

Assign linear resource curve.

Mike planner
User offline. Last seen 18 hours 41 min ago. Offline
Joined: 3 Feb 2011
Posts: 45
Groups: None

Hi, 

 

Thank you for the reply. i checked, it was set to Day. It doesnt show the resource on day on resource assignment tho

 

7170
1.png

 

Many thanks

Mike

Raymund de Laza
User offline. Last seen 51 min 21 sec ago. Offline
Joined: 23 Nov 2009
Posts: 744
Hi, set the resource analysis to daily in the user preferences.