R15.1 - You already have the maximum number of databases configured

5 replies [Last post]
Laurent Issner
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 26 Aug 2019
Posts: 4
Groups: None

Hi All

I have just tried adding a new SQLite db to P6 R15.1 and receive the following message.

 

'You already have the maximum number of databases configured. Please delete an existing configuration before adding a new one'

 

I have deleted a number of db's but continue to receive the message. Have also tried repairing the application from the setup disks but still no good.

Has anyone else come across this issue or heard of it?

Thanks in advance

Laurent

 

 

 

Replies

Zoltan Palffy
User offline. Last seen 15 hours 34 min ago. Offline
Joined: 13 Jul 2009
Posts: 2543
Groups: None

glad that I could help there is always a work around

Zoltan Palffy
User offline. Last seen 15 hours 34 min ago. Offline
Joined: 13 Jul 2009
Posts: 2543
Groups: None

glad that I could help there is always a work around

Laurent Issner
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 26 Aug 2019
Posts: 4
Groups: None

Thanks Zoltan

It works by clicking 'configre' and doing as you say. Clicking 'Add' obviously has issues.

I just counted my DB's and actually have 70+. New DB for each new client, some larger projects have their own DB.

SQLite is great when you have to import multiple xer's for claims etc. Can then easily forward DB to others.

 

Cheers

Laurent

Laurent Issner
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 26 Aug 2019
Posts: 4
Groups: None

Thanks Zoltan

It works by clicking 'configre' and doing as you say. Clicking 'Add' obviously has issues.

I just counted my DB's and actually have 70+. New DB for each new client, some larger projects have their own DB.

SQLite is great when you have to import multiple xer's for claims etc. Can then easily forward DB to others.

 

Cheers

Laurent

Zoltan Palffy
User offline. Last seen 15 hours 34 min ago. Offline
Joined: 13 Jul 2009
Posts: 2543
Groups: None

P6 lets you create 50 databases why do you need so many ?

There is a Workaround:

To create more than 50 database aliases by selecting 'Configure' at the P6 Professional login screen, and entering a new 'Database Alias' name.