Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Scheduling Problem

3 replies [Last post]
Muhammad Saqib
User offline. Last seen 4 years 31 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Hi Everyone,

I am facing an issue after scheduling (F9) in Primavera.

I am working on a Housing project ( Planning Phase) and i am applying milestones between activities.

When i schedule the project on current data date to give me a updated view of my schedule, all dates appear in my activites is same as data date.

Please help me out in this issue.

 

Thanks for your help

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the only way is can happens is that

1. there are no predecrssors to the milestones.

or

2. all of the predecessors have been completed and the milestones are riding the data date

thats it

Muhammad Saqib
User offline. Last seen 4 years 31 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Thanks Anoon for your reply.

But i have logically linked all the activities. Still problem is there. :(

Anoon Iimos
User offline. Last seen 2 years 13 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
First, make sure that your activities were logically linked before pressing F9. Remember, do not enter dates manually, only durations and then play with your mouse for defining logics. Just practice and later on you will enjoy it!