High Rise Building construction activities

6 replies [Last post]
Muhammad Saqib
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Hello Everyone,

I need Primavera P6 Xer files of complete buidling construction project activities, including all relationships and resources loaded.

Please send me the whole project which includes all activities from start to end ,even if somebody has a house project activities.

I am fresher and giving interviews in differenet companies but some interviewer asked me about WBS of building project and foundation activities of building project and some asked me about how many manpower you will used to complete xyz activity.

Now i have choosen this field and i want to learn in a short interval of time and i know site experience is very much needed for being a good planner. 

I really appreciate if someone send me the xer files, excel or pdf related to this subject on this email address

Do Not Publish your email on PP - Use the private message.

 

Thanks in Advance

Replies

Anoon Iimos
User offline. Last seen 3 years 33 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
When I was 12 or 13, I was a helper of a construction laborer. When I was 26, I was doing the so-called planning or scheduling in a foreign country. At my age now, I still don't know or understand which comes first: The Chicken or the Egg? I guess Planning is similar. So you must work and earn the knowledge yourself. It is a good start to learn how to ask the right questions.
Muhammad Saqib
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Dear Mike,

Thanks for the reply and i totally agreed with you. This is the only way to become a good planner.

But i met some people who are very good planner but no or less site experience. I talked to him and they said you need to study and fully understand the BOQ documents and drawings. I think we can breakdown the project into smaller activities through BOQ document, but problem will arise in Resource management which is totally based on manpower productivity, and this experience comes only through by site experience.

Secondly, some people say every company has their own productivity rates standard.  So planner has to used their rates.

I am working in a company where Baseline comes from the client or consultant.We only need to update or sometimes have to modify it.

I am 26 now and if i start my career from the junior site engineer then it takes me much time to go through your suggested way and i cannot afford to do so.

So i want to learn,study all the requirements to become a good planner in a short interval rather than start of my career from the scratch, and i know i did mistake by choosing planning field directly.

Thanks

Regards,

Mike Testro
User offline. Last seen 39 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Muhammad

Sorry but you have to learn that by your own experiiance. Don't try to be a planner until you have learnt how to build it.

My advice is to work as a junior capacity on a construction site for a year or two and get some mud on your boots.

Then move into planning when you are confident.

Best regards

Mike Testro

Muhammad Saqib
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Dear Anoon,

Thanks for the advice and yes you are right,i agreed. But you know some building projects are more or less symmetrical and have almost similar activities. Let's say housing project ,Residential Flats etc.

Actually i need xer files of different projects just to learn how to breakup the project into smaller activities.

Thanks again

 

Regards

Mike Testro
User offline. Last seen 39 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anoon

Although your excelent advice was worth saying twice I have deleted your duplicate post.

Best regards

Mike testro - Moderator

Anoon Iimos
User offline. Last seen 3 years 33 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Every project is unique, building construction may vary from foundation. Depending on design, some may require pile(s) foundation, others may have only raft or spread foundation. Some buildings may have 10 basements, others may have not. I suggest you learn how to build from drawings and specifications. Activities may become typical for some floors, again, depending on specific details. When you learn how to define activities, correspondingly, you must also learn how to calculate quantities. I guess this is the elementary.