Forum Sponsor:

Oracle Construction and Engineering (formerly Primavera) is transforming the world by helping organizations plan, build, and operate critical assets with on-premise and cloud-based project portfolio management solutions.  Learn more about Oracle Construction and Engineering...

We wish a warm welcome to the find people who are offering the ScheduleReader™ application. We hope to add more interesting news here shortly.

Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

On-Going Progress Gap

3 replies [Last post]
Ruel Camaquin
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 16 Nov 2008
Posts: 94

Hi Guys,

Just like to know why is there a gap in updating or progressing on an activity on on-going projects? Also is there a way to mitigate this?

Another, can you guy provide reference guide in making or doing an Delay Impact Schedule?

Thanks in Advance.

Cheer!

Ruel

Replies

Zoltan Palffy
User offline. Last seen 21 hours 3 min ago. Offline
Joined: 13 Jul 2009
Posts: 2076

I do what I can

Ruel Camaquin
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 16 Nov 2008
Posts: 94

Thanks Zoltan! You been a great help to the Primavera P6 Community.

Zoltan Palffy
User offline. Last seen 21 hours 3 min ago. Offline
Joined: 13 Jul 2009
Posts: 2076

select bar and for the actual work bar select Current Bar as the timescale ist the 3rd column from he left under Bars.

for Delat Impact look at At AACE Recommended Practice No. 52R-06 Time Impact Analysis