Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-08-06 13:42 Permalink why not just set the why not just set the threshold and define the critical path to what ever float that you have go to tools schedule options Define critical activities as Total float less than or equal to then put in your value. the other option is to never set a project must finish by date or have a fnish on or before milestone this way the float wil ALWAYS be zero Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-08-06 13:42 Permalink why not just set the why not just set the threshold and define the critical path to what ever float that you have go to tools schedule options Define critical activities as Total float less than or equal to then put in your value. the other option is to never set a project must finish by date or have a fnish on or before milestone this way the float wil ALWAYS be zero
Member for
16 years 3 monthswhy not just set the
why not just set the threshold and define the critical path to what ever float that you have
go to tools
schedule
options
Define critical activities as
Total float less than or equal to
then put in your value.
the other option is to never set a project must finish by date or have a fnish on or before milestone this way the float wil ALWAYS be zero