P6 Professional R16.2 Resource Unit of Measure Administration

2 replies [Last post]
Armando Moriles
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 16 Jan 2018
Posts: 4
Groups: None

Hi all,

Using P6 Professional R16.2, I can't find the administration functionality to add a new Resource "Unit of Measure".

Thank you in advance for the help/assistance.

 

Cheers,

Arman

Replies

Armando Moriles
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 16 Jan 2018
Posts: 4
Groups: None

Hi David,

Thanks for that, very much appreciated. I did find the Unit of Measure in the EPPM Database under Administer pull down menu, then Enterprise Data. However, it seemed I have no authority to add a new unit of measure. I will just talk to our Administrator.

Many thanks again.

 

Regards,

Arman

David Kelly
User offline. Last seen 3 years 9 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Unit of measure for material resorces is managed in the Web client if you have an EPPM database. If you have a PPM database, then it isin the admin pull down under categories