Primavera P6 Schedule Progression and Duration Type

1 reply [Last post]
Emily Foster
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Here's a look at why it is important to set the duration type to fixed duration and units before beginning to progress the schedule in Primavera P6 http://ed.gr/h5p6

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

or fixed duration and units/time becasue if you do not and then add resouces then your mahours that you put in for the resource will determine the duration of the activity.