P6 Professional 16.1 will not add new pred or succ in Window but will using highlight and button combo

4 replies [Last post]
John Reeves
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

P6 Professional 16.1 will not add new pred or succ in Window but will using highlight and button combo.  It is almost as if something is keeping the add activity window from popping up.  I will pop up if I click an existing predecessor and change it but will not if there are no predecessors.  Same with successors.  I can work around not being able to just simple add a new predecessor by just using the activity above it using highlighting and the top ribbon button and then change it - but I assume this is a bug or something.  I made sure I allowed popups, at least I thougtht I did in the correct spot.  Odd thing is that it has worked fine for a year.  Any ideas?

Replies

Marsha Peterson
User offline. Last seen 7 years 1 day ago. Offline
Joined: 4 Mar 2004
Posts: 19
Groups: None

Let me know if it doesn't work....  I like new best pals..... 

John Reeves
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Genius!  I am not able to verify at this moment but that exactly fits my scenario....Thank you so very much.  In the old days...we would just slowly go insane with these issues, and by old days I mean just prior to your response.  I guess I did not bother seeing if Oracle has a forum, somehow I thought my odds were better here.  Your new best pal, John. 

John Reeves
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Genius!  I am not able to verify at this moment but that exactly fits my scenario....Thank you so very much.  In the old days...we would just slowly go insane with these issues, and by old days I mean just prior to your response.  I guess I did not bother seeing if Oracle has a forum, somehow I thought my odds were better here.  Your new best pal, John. 

Marsha Peterson
User offline. Last seen 7 years 1 day ago. Offline
Joined: 4 Mar 2004
Posts: 19
Groups: None

I think I've answered this before, perhaps in a different forum.  Let me tell you that the same thing happened to me when I was using my laptop with an additional monitor I don't always use.  It appeared that when I went back to using just my laptop monitor, I'd left some of the Primavera windows on the additional monitor, and when I closed they stayed there.  I finally plugged in an addtional monitor again to my laptop and saw my missing detail windows sitting there, patiently waiting for my next action.....

See if this helps....