Collapsing and Expanding Sub Projects

2 replies [Last post]
Emma Lang
User offline. Last seen 3 years 9 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

I'm trying to collapse some but not all of the sub projects I have. Group and sort does it to a certain level, but is there a quick way to select a number of sub projects and expand or collapse them without having to affect the whole schedule?

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 10 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

you have 2 options

option #1

you can filter your projects that you want to collapse and expand 

 

option #2 

you can create a Project Portfolio and put the projects in there that you want to collapse and expand

David Kelly
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

All you have is "Collapse to". So if you need to open up some rojects that are at Level 1 and other at level 4 and none in between you will be doing a LOT of clicking.