Only EPS is visible

6 replies [Last post]
Md Sakib Islam
User offline. Last seen 52 weeks 9 hours ago. Offline
Joined: 22 Aug 2015
Posts: 9

Hi,

(Somebody please help)

I am using P6 R8.4 web

Since last two days I am upset that I am not able to see my projects. Even I am not able to create new projects.

Please check the snap shot.

When I asked the IT help desk they told its admin problem. and when i contacted admin he is denying. I think I dont have administrative previlages. But I dont have any evidence as well.

 

4255
p6_issue.jpg

Replies

Zoltan Palffy
User offline. Last seen 4 days 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

I thought so 

Md Sakib Islam
User offline. Last seen 52 weeks 9 hours ago. Offline
Joined: 22 Aug 2015
Posts: 9

Tomasz Szłapazoltan palffy

thankful to you for your help. it was admin previleges that has been sorted out.

Zoltan Palffy
User offline. Last seen 4 days 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

check your security profile make sure you have the proper rights 

Tomasz Szłapa
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 8 Jan 2016
Posts: 7

If it's not a filter issue so it has to be something wrong with your privileges. Send this screenshot to admin and add in comment that the project in top menu is disabled.

Md Sakib Islam
User offline. Last seen 52 weeks 9 hours ago. Offline
Joined: 22 Aug 2015
Posts: 9

It is already off. I checked. There might be some other reason. Thanks a lot for your reply. is there any other reason ? I already checked filter, group and sort but everything is ok. Even I am not able to create any new project in any of the EPS. Only resources are visible. 

Tomasz Szłapa
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 8 Jan 2016
Posts: 7

Hi,

 

you have turned on All EPS Elements filter, just turn it off.