Labour units problem while converting form P3 to P6

1 reply [Last post]
Muhammad Imran
User offline. Last seen 9 years 51 weeks ago. Offline
Joined: 19 Sep 2013
Posts: 6
Groups: GPC Qatar

Dear all,

While converting P3 file to P6, a problem is faced that Manhours assigned to activities as Labour unit in P3 formate becomes Non labour units after convertion to P6, which crearts problem in calculation of Project Progress/Level-1 Summary as well.

 

Kindly help me in this regard.

 

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

I have never seen this