Importing Excel date to P6

2 replies [Last post]
Krishna prasad Ph...
User offline. Last seen 9 years 51 weeks ago. Offline
Joined: 22 Dec 2011
Posts: 6

1.       While importing from XL, Actual Dates are updating and Physical % Complete is not updating

2.       Even If Physical % complete is updated manually, Remaining Duration is not changing

3.       Actual Expense cost is also imported, but not updated in Schedule

 

 

Any body please help in this regards. I doubt i am missing some important step in the process of importing. Any body can help me mentioning step by step procedure for successful import

Replies

Zoltan Palffy
User offline. Last seen 4 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

make sure that % complete type is duration and export the duration % complete the actula start date and the actual finish date to excel update the three items in excel and import back into p6

Nafees Ghouri
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 26 Mar 2012
Posts: 9
I have activities to get the % completion from quantities. The quantities measuring units are not similar, which is usually the case. I need to know the correct way to get the project % completion in excel and then later transform into P6. Appreciate if someone guide me in steps.   thanks NG
Zoltan Palffy
User offline. Last seen 4 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

first make sure that you have the proper rights to import information

1. you can only import actual dates, and constraint dates and these dated need to have the correcr format was well as the correct TIMES. Physcial % complete must be in the correct format. Why not export an activity with these items and use it as a template for importing the new information.

 

2. That is correct when using physical % complete it DOES NOT update remaing duration because remaing duration is assoicated with duration % complete. In order to use physical % complete to update remaining duration run a global change where duration % complete equals physical % complete

3. make sure that the format is correct