SCHEDULE HEALTH-CHECK

6 replies [Last post]
Neda Nejad
User offline. Last seen 10 years 12 weeks ago. Offline
Joined: 22 May 2013
Posts: 6
Groups: None

Hi Folks,

 

Doesn any one know how to run schedule health-check after updating schedule for %complete/atcual cost on a weekly basis in EPC and FEED?

 

Neda

Replies

Neda Nejad
User offline. Last seen 10 years 12 weeks ago. Offline
Joined: 22 May 2013
Posts: 6
Groups: None

Hi Zoltan,

 

TX alot for the links very helpful.

Zoltan Palffy
User offline. Last seen 10 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

The (DCMA) Defense Contract Management Agency has a guide line that they have called a DCMA 14 Point Schedule Assessment. This 14 point check  is used to determing the overall quality and performance of the cpm schedule.

listed below is the link to the DCMA documentation

 

http://www.dcma.mil/policy/200-1/PAM-200-1.pdf

https://www.plannertuts.com/dcma-14-point-schedule-assessment/

There is also a free add on tool for excel called xertool kit. This uses and existing xer file to help gather the stastics to perform the elements of the 14 point assessment. Here is the link

http://www.xertoolkit.co.uk/#All

Neda Nejad
User offline. Last seen 10 years 12 weeks ago. Offline
Joined: 22 May 2013
Posts: 6
Groups: None

Hi

 

Tom TX for ur docs. they are really invaluable!

Neda Nejad
User offline. Last seen 10 years 12 weeks ago. Offline
Joined: 22 May 2013
Posts: 6
Groups: None

Tom tx for ur email I sent u a dummy email so that u can come to me with ur materials.

Larry TX for ur help I am on P6.

Tom Reichner
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 23 Nov 2011
Posts: 46

Neda,

 

A few years ago I was faced with a similar situation and I did not have any software to perform schedule metrics tests. So I developed a series of filters to check the metrics, and wrote a paper on how to construct these Quality Control filters. I wrote this paper for Primavera, and a similar paper for Microsoft Project.

 

If you will send your email address to treichner@yahoo.com, I will be happy to send both papers by return email.

Larry Beards
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 19 Jun 2012
Posts: 3

Hi Neda

This is the first time I have offered assistance so you wil have to excuse any errors in process.

 

The first question to answer is what planning software are you using and what version. Bases on the answer I could suggest possible solutions.