Activity Leveling Priority

1 reply [Last post]
Harold Forsberg
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 15 Aug 2001
Posts: 20
Groups: None

I have a schedule with a concrete resource loaded agaianst several hundred activities.  The concrete activties have been prioritized using the "Activity Leveling Priority".  When viewing the Resource Assignment screen, I used to be able to group by the "Activity Leveling Priority" but this option appears to have disappeared.

I have tried to run the P6 repair program from the Windows Control Panel, but since this version was installed by the vendor, I =nver received the installation cd.

Any suggestions on how to get my resources grouped by the "Activity Leveling Priority"

 

Tnaks in adavnce for any help

 

Replies

Raymund de Laza
User offline. Last seen 35 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Harold,

Activity Leveling Priority data can be viewed only from the Activity Pane.

 

Regards,