Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

% Complete Type

6 replies [Last post]
Jong In Choi
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 24 May 2012
Posts: 4
Groups: None

Dear, Everybody

I would like to know how to  change the " % complete type" is "physical" in all of activities.

I can't find way to use "fill up", "global change"..

Only way is to change each activities?

I need your help please.

 

 

Replies

Xenia Marami
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Feng Benjamin
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 1 Feb 2011
Posts: 12
Groups: None

Hi,

You can do a fill down to achieve that.

Under "View", Choose "Columns" or click on the respective shortcut.

Open the column "Percent Complete Type" 

This will list the % Complete Type of all activities. You can then do a select and fill down.

Regards,

Benjamin