% Complete Type

6 replies [Last post]
Jong In Choi
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 24 May 2012
Posts: 4
Groups: None

Dear, Everybody

I would like to know how to  change the " % complete type" is "physical" in all of activities.

I can't find way to use "fill up", "global change"..

Only way is to change each activities?

I need your help please.

 

 

Replies

Xenia Marami
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Xenia Marami
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 24 Feb 2014
Posts: 8
Groups: None

please can you explain how this field is opoen for completion , after it is revealed.

Feng Benjamin
User offline. Last seen 2 years 50 weeks ago. Offline
Joined: 1 Feb 2011
Posts: 12
Groups: None

Hi,

You can do a fill down to achieve that.

Under "View", Choose "Columns" or click on the respective shortcut.

Open the column "Percent Complete Type" 

This will list the % Complete Type of all activities. You can then do a select and fill down.

Regards,

Benjamin