activity usage profile - Need to Show Values

3 replies [Last post]
Premod Jacob
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 16 Nov 2013
Posts: 3
Groups: None

Hi,

Good Day !!

 

Is sit possible to show the unit values at the top of each bars in Activity Usage Profile Histogram in P6..?

Replies

Raymund de Laza
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

That's not possible. Suggest to Transfer the Data to Excel.

Premod Jacob
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 16 Nov 2013
Posts: 3
Groups: None

Hi De Laza,

I want that labels / values in the Acivity Usage Profile Histogram, not in Ghant Chart.

Is there any option to give a label / unit in that Histogram printout ?

Raymund de Laza
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Jacob,

Use the Bar Labels.