Schedule Template for Regulating Tank

5 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

Can you provide me with the main activities for tank constructing to include it in the schedule?

Regards,

Moutaz

Replies

Syed Hussain
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Oct 2012
Posts: 17
Groups: None

Moutaz,

I was finally able to upload the image.

1703
tank_fabrication.jpg

Syed Hussain

Syed Hussain
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Oct 2012
Posts: 17
Groups: None

Sorry. didn't work. 

 

Syed Hussain

Syed Hussain
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Oct 2012
Posts: 17
Groups: None

Moutaz,

I have added only logical links. Some activities don't have any predecessor as they are independent and can be started any time depending on resources or material availability. I am uploading image first time and don't know how will it look like.

<a href="http://s1279.photobucket.com/user/syedhussain79/media/Tankfabrication_zps231d8055.jpg.html" target="_blank"><img src="http://i1279.photobucket.com/albums/y531/syedhussain79/Tankfabrication_zps231d8055.jpg" border="0" alt=" photo Tankfabrication_zps231d8055.jpg"/></a>

 

Syed Hussain

moutaz aldeib
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Sir,

Thanks a lot for your feedback, the details I am looking for is level III and my concern is the sequence between the activities.

Regards,

Moutaz

Syed Hussain
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 11 Oct 2012
Posts: 17
Groups: None

Moutaz,

I don't know how much details you need but I am listing all major activities.

Tank top:

Plate ends preparation,laying of plates on ground as per layout, Tacking of plates, marking, cutting, welding(both sides), edge bending, reinforcement ribs(if required)

Tank Bottom:

Same activities as for top.

Shells:

Same activities as for top with difference that edge bending will be replaced with shell rolling. No of shells depend upon height of the tank.

Accessories:

Manholes and nozzles will be fabricated as per design.

Fitup of tank technique is different for different sizes. For small tanks, fitup can be started from bottom ie bottom is placed on ground or foundation and then shells are fitted one by one and finally top is fitted. For big tank, it is better to start fitup from top ang keep on lifting the top while adding shells and finally bottom of the tank. This method is used to avoid scaffolding work. Discuss with your fabrication team about it. Nozzles and manhole are fitted after complete fitup of the tank. Don't forget to list down internal welding work as it takes very long time depends upon plate thickness and number of passes.

 

Syed Hussain