Task Name / Date used in a movie column

1 reply [Last post]
Thich Phet
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 23 Jun 2020
Posts: 3
Groups: None

Hi,

I'm managing several project schedules all of which have the milestone task GoLive. I want to be able to capture the date into a movie date column I've created. Is there a way to do this via a formula or other method?

Many thanks for your help.

Replies

Tom Boyle
User offline. Last seen 22 hours 54 min ago. Offline
Joined: 28 Nov 2006
Posts: 280
Groups: None

Thich Phet,

What's a "movie date column"?

If you want to capture a date from one task (the GoLive milestone) and display it for other tasks, then you can't to that with formulas (in general).  Simplest would be to copy-paste the cells where you want them.