Link between RD & P%C
Wed, 2012-08-08 10:06
Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?
Thu, 2012-08-30 09:07
#1
James,
Physical Percent Complete cannot be linked to Actual / Remaining Duration
Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default
Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically
Alexandre
Replies