Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?
Link between RD & P%C
Forum Sponsor
Top Posters
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
James,
Physical Percent Complete cannot be linked to Actual / Remaining Duration
Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default
Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically
Alexandre