Link between RD & P%C

1 reply [Last post]
James Braghini
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 10 Sep 2010
Points: 22

Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?

Replies

Alexandre Faulx-B...
User offline. Last seen 2 days 9 hours ago. Offline

James,

Physical Percent Complete cannot be linked to Actual / Remaining Duration

Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default

Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically

Alexandre

Market Place

Providing permanent and interim planning related recruitment solutions to a range of contractor and consultancy organisations.
Books and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself or run your own in-house or public planning courses.
EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders
A recruitment and consulting organisation that provides services to the European nuclear industry.
We want to build software that solves real problems, allow people to work more productive and happier.