Attaching comments

1 reply [Last post]
Craig Adams
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71
Hello,

Sorry in advance if this is already here, I couldn’t find the answer in my search.

Want to attach a text box with a arrow pointing back to a baseline bar as an explanation as to why a task was delayed. Have been able to make the text box in the gant view but not attach it to the baseline task so if I cahnge the view it stay put.

Kind regards for your answers in advance.

Craig

Replies

Craig Adams
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71
Meant to put this in the Ms Project 2007 section.