activity type

2 replies [Last post]
Jon Ward
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60
sorry one other P3 to MS Project question,,
how do i determin the type of task,, at the minute , by default all activities are activities,, how do i create a milestone?
many thanks

Replies

Chee Sean Moo
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 21 Dec 2006
Posts: 12
Groups: GPC Malaysia
Just to reply for fun.

MSP is not allowed to define activities type like P3/P6, the activities will automatically change to milestone when you assign the duration to 0.

But MSP (compare w/ P3) is allow to create hyperlink within cell value, make use for it, you will found more fun!!! ;)
Jon Ward
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60
ignore that question,, just answered it myself