Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

activity type

2 replies [Last post]
Jon Ward
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60
sorry one other P3 to MS Project question,,
how do i determin the type of task,, at the minute , by default all activities are activities,, how do i create a milestone?
many thanks

Replies

Chee Sean Moo
User offline. Last seen 5 years 13 weeks ago. Offline
Joined: 21 Dec 2006
Posts: 12
Groups: GPC Malaysia
Just to reply for fun.

MSP is not allowed to define activities type like P3/P6, the activities will automatically change to milestone when you assign the duration to 0.

But MSP (compare w/ P3) is allow to create hyperlink within cell value, make use for it, you will found more fun!!! ;)
Jon Ward
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60
ignore that question,, just answered it myself