Hello all,
Ive seen the following expression on a web site related to Project 2007 for the definition of FNET constraint:
-----------------------------------------------------------
(Scheduled)ES=(Calculated)ES + Delay
Finish No Earlier Than: Schedules the task to finish on or after the constraint date.
-----------------------------------------------------------
FNET concept is very clear to me but I didnt get what
s/he meant by this expression.
I believe there is no "scheduled early start" concept. It
is also calculated by Project by using CPM on the background, Is it correct ? You dont schedule early
start, it is calculated.
Thats the URL:
http://ossmall.info/2008/01/17/definition-of-microsoft-project-constraints/
I am OK with this one: for MSO it says EF,LF,SF=CD. MSO means zero slack so EF=LF and scheduled finish (SF). I guess SF is what we see on the Finish Date task field.
Thank you for any feedback, I really appreciate it.
Best Regards.
Replies