Planned Strat / Early Start

2 replies [Last post]
Shahzad Sikandar
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
What is difference between Planned Start and Early Start dates?

how do i mangage these dates in schedule?

Replies

Shahzad Sikandar
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
thanks Kosa
Darren Kosa
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None
Hi Shahzad,

By Planned Start, I assume you mean the dates in the ’Start’ column relating to the scheduled dates the tasks are due / planned to begin?

These dates are determined by MS Project based on a combination of calendar (project or task), precedence (task dependencies) or constraints (ASAP etc).

The Early Start date are determined by backward and forward passes (ES / EF / LS / LF), taking into account Float (Slack in MS Project). Depending on whether the project is scheduled from the Start Date or a known Finish Date (most are scheduled from the Start Date) the Early Start will be the same as the Planned / Scheduled Start.

When updating / progressing a schedule you can also use Actual Start, but that’s another story for another time...