Resources

1 reply [Last post]
HHM HHM
User offline. Last seen 11 years 9 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 5
Groups: None
Pleas , may you advise my about how I can automatically increased the assigned resources ? To reschedule and managed the actual delay to achieve the original finish date of project ,as per the base line program???

Replies

Zhang Haixiang
User offline. Last seen 5 years 18 hours ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
I think you need to update the resource assignment manually,
the program do not know which resource should be increased for which task.
In general, you may check all critical tasks to find out the tasks that their duration can be shortened
to shorten the duration, you need to increase resource, try to start with the cheapest ( cost effective)