MsProject to P3 PP

15 replies [Last post]
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Guys and Girlies,

I know we have been discussing this issue for quite a long time but still I believe have not come to a single solution.

I need to transfer a MsProject 2000 file into Primavera P3 version 3.1. What is the best way to do that ?

Many thanks in advance

Replies

Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Sorry, it is of course utility that produces the error.
Will send you a file down today

Thanks
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
MsProject

The file has about 1000 activities and it is about 2 MB
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Alex,

When I try to convert small projects with 10-15 activities it works OK, but as I try bigger ones it shows "Run-time error ’5’, Invalid procedure call or argument.

Thanks
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Alex,

Thanks for the file, it works OK with small projects but does not work with big ones (about 1000 activities)
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Thanks Alexandre,

I am new to this forum, do not know how to send PM. My e-mail address is farid.salmanov@rolls-royce.com. Can you please send this to that account.

Thanks in advance
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Thanks Paul,

This under tools is P3 to MPX and vice versa converter.
To use this I need my mpp file transferred to mpx, and I use MsProject 2000. How can I transfer mpp into mpx, that’s my bottleneck
Paul Harris
User offline. Last seen 9 weeks 4 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
This is a P3 menu item under Tools.

Regards

Paul E Harris
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Thanks Paul

I have downloaded the article and figured out the way I can do transfer.

The question I have got now is: in your article you refer to "MPP to MPX conversion utility" availability at the Primavera.com but I could not find it there, do you have this software available in your possession if yes, can you please me at farid.salmanov@rolls-royce.com

Many thanks in advance
Paul Harris
User offline. Last seen 9 weeks 4 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
Farid Salmanov
User offline. Last seen 18 years 49 weeks ago. Offline
Joined: 15 Apr 2006
Posts: 16
Dear Paul,

Thanks for your feedback but I did not manage to download that article from your web-site, can you please paste the exact link of the article’s whereabout

Many thanks in advance
Paul Harris
User offline. Last seen 9 weeks 4 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
There are several methods and they all have advantages and disadvantages. There is a technical article on my web site that may assist.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au