Task Levelling when Tasks Completed
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Thanks very much for the tip - Ill give it a go.
Regards,
Steve
Steve
Microsoft Project does not have a strong leveling engine.
The only method I know to stop this type of messing around where MSP levels completed work and ignores Actual Dates, which is not too clever and very frustrating, is to display the Resource Usage Sheet in the bottom pane and enter the actual hours against the completed work. This also changes the Resource Contour to “Contoured”. It may then level as you hope.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au