Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Final EOT Entitlement Calculation

No replies
Mohamed Basheer
User offline. Last seen 1 year 26 weeks ago. Offline
Joined: 23 Jun 2009
Posts: 6

As per the delay anaysis total 4 months delay happened. Contractor is responsible for 3 months and owner responsible for 1 month. 

Is contractor entieled for time extension for this 1 month delay by owner.

How to calcuate final delay assessment after the cases like this?  

Mike Testro
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Mohamed

If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs.

But the contract that you signed may not allow this.

Best regards Mike T.