Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EOT calculation

5 replies [Last post]
Kannan CP
User offline. Last seen 46 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

In the delay analysis, due to an Employer, delay the Contractor is claiming for for an EOT of 100 days. This is through a certain path in the programme.

At the same data date of above the Contractor is in delay through another path#2 by 40 days.

The above paths are not interlinked. Is the Contractor entitled for entire 100 days with prolongation cost of 60 days? or only entitled for 60 days of EOT and the prolongation cost for 60 days?

Thanks

Best Regards

Kannan

Replies

Kannan CP
User offline. Last seen 46 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks mike...

Mike Testro
User offline. Last seen 26 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Kanan

If the employer caused 100 days delay the contractor gets an EoT of 100 days + releif from LAD's

The Contractor then gets costs for the remaining 60 days.

Best regards

Mike Testro

Kannan CP
User offline. Last seen 46 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mike,

Thanks for the reply.

As per the contract there is only one milestone for the overall completion of the project. Can the Client issue penalty to the Contractor when the Contractor is unable to complete the overall project due to the delay event by the owner?

Instead of that is it sense to calculate the EOT as 60 days (100-40) with the prolongation cost for 60 days?

 

Best Regards

Kannan

Mike Testro
User offline. Last seen 26 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Kannan

It seems that you are describing Concurrent Effect rather than Concurrent Cause.

This is where two or more events arise in different time zones in the baseline but each delay the works during the same extended time zone.

So the Employer caused 100 days delay and the Contractor caused 40 days delay.

In this simple scenario the contractor gets EoT for 100 days pays 40 days LAD's and gets 60 days prolongation costs.

If it was the other way round the contractor would get EoT for 40 days pay LAD's for 60 days and no costs.

Best regards

Mike Testro

Patrick Weaver
User offline. Last seen 1 hour 46 min ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

The answer is 'it depends........

concurrent delays are a very difficult area, see: http://www.mosaicprojects.com.au/WhitePapers/WP1064_Concurrent-Delays.pdf