Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delay due to re-design

5 replies [Last post]
Sunil Babu
User offline. Last seen 5 years 41 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Dear All,

This delay happened in the mid of a project. After completion of a foundation there was a design change and additional floor to the building due the re-design and strengthening of foundation, some delay (due to abortive works @ 3months) happened. Now the situation is in such a mess that contractor has to revise the programme to include new scope and abortive works causing an overall delay of more than 6 months. Also some handed over areas again delayed due to additional soil stabilization works to be carried out by another contractor. How can be modify the Baseline inorder to incorporate all these changes ?

Your comments will highly appreciated.

Best Regards,

Sunil.

Replies

Mike Testro
User offline. Last seen 24 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Sunil

Splitting the task will work.

Best regards

Mike Testro

Kannan CP
User offline. Last seen 44 weeks 5 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Sunil,

As you said, splitting of activities/phases can help to identify the partial handover stages.

 

Best Regards

Kannan

Sunil Babu
User offline. Last seen 5 years 41 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Mike / Kannan,

Thanks for your reply. Actually the revised Baseline reflecting all the current delays such as late handover dates, late issue of IFC drawings, Stop instructions due to re-design, Abortive works etc. My question is some areas there are partial stop and partial start of works also partial hanover of areas in milestone key dates how can we reflect these partial things it should be either zero percent or 100% . I believe split of activities will be a solution. Also stop event and start event and link  to the corresponding activites.

Best Regards,

Sunil.

Kannan CP
User offline. Last seen 44 weeks 5 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Sunil,

I believe the origin of the revised baseline will be from the last updated schedule, just before the variation of design. It is to be noted that the Contractor may finished the foundation with a delay.

So I suggest to update the programme up to the completion of foundation (with out adding the design change or late site access). This may show a delay in completion date because of Contractor. After this incorporate the revised scope and the late access, which will show the real revised completion date and Contractor's entitlement for EOT.

Since the additional scope includes additional amount this leads to a revised S-CURVE. The percentage progress achieved as of today will also change, because the total budgeted cost is changing. If the revised S-CURVE is preparing from the updated schedule (the revised baseline), for the completed time period, it is to be assumed that the plan percentage is equal to the actual percentage, and the remaining percentage from the balance cost distribution(including new scope) up to the Project end.

If you want to show the completed period percentage as similar to the original baseline program, I think (not 100% sure) the revised scope and the lateness of site access is to be included in the original baseline. The start date of the revised scope can be added in line with the actual instruction received from Client. Then it can be linked to the relevant construction activities.

Best Regards

Kannan

 

Mike Testro
User offline. Last seen 24 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Sunil

Place the events into the programme as "tasks" and link them to the delayed activities.

Best regards

Mike Testro