Prolongation costs in case of pacing delays

3 replies [Last post]
aqil mahmood
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 19 Aug 2005
Posts: 18
Groups: None
Hi If a contractor decided himself to pace non affected work with ongong affected works, whether he would be eligible for prolongation costs? Or his delay in non affected areas woul be treated as concurrent delays that will not entitle him any prolongation costs? Regards

Replies

Mike Testro
User offline. Last seen 24 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Aqil

I agree that a notice of pacing is good practice but it is rarely done.

I would suggest my ebook - Principles of Delay Analysis - will give you a good insight into delay analysis procedures.

It can be downloaded from my website www.expertdelayanalysis.com for £75.00

Best regards

Mike Testro

aqil mahmood
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 19 Aug 2005
Posts: 18
Groups: None
Thanks mike It means if contractor hasnt provided advance notice to the client that he will be pacing his activities with employers delay event, this will be treated as his concurrent delay? Also could u plz advise me some good books on evaluating extension of time and prolongation costs. Many thanks
Mike Testro
User offline. Last seen 24 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Aqil

Extension of time are separate to claims for costs.

Pacing will not affect an EoT award but it will be taken into account when assessing and prolongation / disruption costs as it is very difficult to prove pacing is not delay.

Best regards

Mike Testro