Primavera Contracts Manager

3 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 4 years 6 days ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear All,

In a few days we are going to procure the Primavera contracts manager , can any of you give there advice as to what preparation we need to do and we should be expecting in the first few days.
regards

deb


Replies

Pranab Kumar Deb
User offline. Last seen 4 years 6 days ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear Mr.Samar and Mr. Catalan ,

Thank you very much your comments are very helpful and much appreciated.
any further information with any one??

regards

deb
R. Catalan
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Pranab,

Got trained last year using ver. 11.

Get ready with the following:
- Let PD/PM decide on who can access what info
- Contact lists/company directory
- Forms/templates for all docs. in PCM (Letters, Transmittals, MOMs, RFIs, etc.)
- Define cost codes in PCM (cost accounts in P6), collaboration point for these 2 Primavera softwares

HTH,
R. Catalan
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Pranab,

The small information that I have, you need the following:

1. computer with XP pro installed
2. web based application (internet)
3. MS SQL server 2005.

Also, I know that the current verion will be useless when the 64 bit version is out in few months/ year.

Each project is divided into 4 major sections:
I. Project Information
II. Communication
III. Contract Information
IV. Logs.

I should be running a project using it soon. And will let you know more details.

Best Regards,

Samer