Change Order VS Variation Order

8 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear All,
I also wanted to know the difference between change order and variation order.
Regards
deb

Replies

ashraf alawady
User offline. Last seen 10 years 34 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
No difference in terms of change order and variation order
Thanks
Pranab Kumar Deb
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Thanks Anoon and Ashraf i believe i got the point.
regards
deb
Ashraf Jahangeer
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Deb,

Anoon is right as there are also in some contracts like I have a term called "Adjustment Order".

So it all depends upon how the term is defined in your Contract.

Regards,

Ashraf
Anoon Iimos
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
if it’s defined in your Contract, then that’s the definition, otherwise, forget it! i suppose Variations and Change Orders got the same intent
Pranab Kumar Deb
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
hello anoon , then tell me what si change order
regards
deb
Anoon Iimos
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
then you work on Variations and Adjustments, forget Change Orders!
Pranab Kumar Deb
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello Anoon,
My contract mentions "variation" -any change to the works , which is instructed or approved as a variation under clause 13( Variations and Adjustments ).
Change order is not mentioned
regards
deb
Anoon Iimos
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
what does your Contract says?