Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Error in pricing

7 replies [Last post]
Raphael Adeyemi, ...
User offline. Last seen 9 years 33 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
I am presently on a water project under FIDIC hybrid contract in which few fitting items were priced say BHD100,000.00 instead of BHD100.00. I guess thi was as a result of coma wrongly. The contract is in operation for over a yr. It was not discover at the tender evaluation process.

The question is The Consultant has issued instruction for the items not to be purchased and intend to varied the item. The Contractor is of the opinion that he is entitled to loss of expected profit as this amount to over 10% of the total contract.

My opinion is that the Consultant is trying to correct the mistake made at the tender evaluation and using Caluse 51.1 to varied the work. But I am in doubt if the Contractor is entitled to loss of expected profit. What do you think?

Awaiting response from u guys

Replies

Bolisetti Jogiraju
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi Raphael !

You are most welcome.

Cheers

Your friend
Raju
Raphael Adeyemi, ...
User offline. Last seen 9 years 33 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
Thanks , the contract provision herein is 10% as opposed to 15% in Bahrain
Bolisetti Jogiraju
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi Raphael !
Agreed by all that its a mistake at the time of tender evaluation,but when noticed during executing the contract,obviously Consultant will try to vary that particular item.
Unfortunately,Contractor has only one last chance to win his claim for "loss of expected profit(If any arises,later)" under Clause 52.3 (Variations exceeding 15 per cent) of FIDIC.
As you mentioned,its contributing over 10% of contract sum but not yet exceeds 15% .
So,in my openion,the plain answer is NO until it satisfy the above said clause.

Cheers
Dev Tamboli
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 3 Jun 2007
Posts: 28
Groups: None
as far as contract is concerned since it is freezed consultant cant say no to pay for the work you have done at the same rate you quoted in you contract. but for the part or whole fo the work you have not done consultant can take off that work from you as per conditions consultant have a right to take of part of the work from contractor.
after taking off this work from you consultant can ask you to give your corrected rate and then he can award you that work again with corrected rate by showing some variation.
so conclusion is that if you have done the work already you are entitled tot he amount but if you have not done the work and consultant knows about the mistake then bowl is in his court.
Shahzad Munawar
User offline. Last seen 8 years 51 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None

In your case you may claim loss of expected profit as it is explicitly mistaken by the Consultant’s part at the time of tendering.
A D
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Also, the contractor shall claim for the overheads booked for the total cost. He should ask for this extra amount of Overheads also apart from claim for loss of expected profit.

Cheers,

Raviraj
Faried Khan
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None

Hi Raph,

I believe the Consultant has the right to instruct variation under Clause 51, and also the Contractor has the right to Claim loss of expected profit