Contract Price - Variation under FIDIC
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Dear Mithun,
We have two issues here: 1) Compensation 2) Variations.
After confirming that your Contract Conditions allows you to claim for both, then you an proceed with the following:
1) Notifying the Engineer as soon as the variation or the rise in prices occur.
2) Supporting the claim with all possible documents as soon as possible.
3) In case you have new items, then the price can be derived from similar items in the BOQ. Or, if it is a totally new item, then you an do proper Price Analysis with all necessary supporting data.
The Conditions of Contract supported with the FIDIC documents should be clear enough to judge what you are entitled to.
Best Regards,
Samer