Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Release From Performance Under Cl. 66.1 FIDIC 4th

9 replies [Last post]
Faried Khan
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None
Hi All,

I wish to seek your valuable experience and learn your opinion for the case I have here which I have encountered:

- I am a QS working for a Governmental Department
- I was asked to prepare a report responding to a Contractor’s claim of termination.
- The Termination of the Contract was made by the Department under "Release From Performance" clause of FIDIC 4th Edition "Clause 66.1"
- There was no particular reason for termination except that the Department has decided to sell the Land on which the project was intended to be built upon.
- The Payment as per this situation should be made in accordance with Clause 65.8.

My Question is as follows:
- Is the Termination "Release From Performance" procedure is correct i.e. is it the Correct Clause to use for this situation?!
- Clause 65.8 doesn’t give the right for reimbursement of loss or damage (or even loss of profit), but the Contractor has include such item in his Termination claim, so is he really entitled for such compensation?
- For General items (Prelims) is it the cost of those items should be consider only proven by actual invoices, time sheets, vouchers ..etc, or as per the rates set out in the BOQ as if they were permanent work items.
- Finally, if Clause 65.8 is not giving the entitlement for reimbursement for loss or damage. Can the Contractor seek such compensation under the Governing law?, and how it could be quantified?

Thanks in advance for your professional help

Replies

Philip Jonker
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Hesham,

Something that came to mind, that is good practice, is to get the contractor to provide a schedule of P&G rates, after the award, to provide an indication of how he will be claiming P&G’s on a monthly basis. This might in this case be 20/20 vision, but the reason for it, is just what is required in your instance, to support both yourself and the contractor in this type of claim. This will give an idea of indirect costs, as opposed to direct costs (which is measurable). The negotiations around the P&G cashflow, can be sorted out prior to mobilisation at the award stage, and as such obviate the problems of front loading,etc.

The problem is that site establishment/mobilisation costs can form a substantial portion of the P&G’s, and simularly demobilisation. In this instance, if the mobilisation/site establishment, had taken place, I believe the contractor is equally entitled to demobilisation costs, which would occur at the end of the P&G cashflow curve. So to summarise the contractor if established, has a right to the front- and rear end of the P&G curve in terms of the fact that he has mobilised, your dept sold the property, and he had to demobilise.

I hope this makes sense.

Regards

Philip
Faried Khan
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None
Thanks Philip for your help and sorry for bothering you, actually the Contractor has completed the mobilization, and even started minor construction works, the main two points that he was arguing is the basis of payment of General Requirements, which I was insisting that it should be against proof of the respective actual expenditure, but he wanted to use the BoQ rates, noting that most of BoQ rates related to such Prelims are exaggerated, and clearly used for (Front Loading)of the project value, knowing that it is lump sum project and no detailed BoQ provided only simplified itemized BoQ, however, the second argument was how would I compensate him for loss of profit which in my opinion it should either based on negotiation or alternatively he should prove such loss (Which I believe it is one hell of an exercise for him to carry out) but he wants to be based upon the proposed percentage inserted by him in the tender, which in reality it’s theoretical and even as per the contract document optional to be used as guide only at the sole discretion of the Engineer ... I think it is a long story though it seems so simple... thanks again for your professional view
Philip Jonker
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Sayed,

My opinions are probably close to those of Bryan. However, the question is what state of readiness (Progress in terms of mobilisation) was the contractor. Had he mobilised staff, pre project planning, was there any project related equipment purchased, how much effort was spent to prepare other than tendering (this is supposed to be carried as an overhead in normal terms) and was the contractor made aware of the possibility of cancelation of contract due to the possibility of the sale of the land. We live in different cultures, and fidics is not always suitable to the law under which it is effected. I have some experience of laws as practiced in Qatar, however, in general I believe the law is fair and will practice this fairness, in normal terms. In english law they have a term ’common law’ which refers to the way way the law is understood by most people. I believe that Islam law has simular precedents,and as such the fairness of the situation should be looked at. In other words, if the contractor accepted the contract, started mobilising, which he spent money on, and was then dropped, he is entitled to his expenses, and as a result a portion of the profits in relation to his expenses.

By not taking this approach, and going for the cutthroat way, as dictated by the Fidics clauses, you can be doing your department irreparible damage in terms of future tenders, as the tender prices will be increased, in case more projects are abandoned, as the land prices are escalating, and the possibility is there to make more profits by cancelling further projects.

The point is that if in this situation, the contractor loses money he has spent other than tendering, pay him on the basis, of the proof of expenditure, and settle the profits on the same basis, to preserve your department’s integrity.

Forget the clauses an remain honest. Obviously the profit from the sale of the land was the carrot, and any good judge will see this.

Maybe try the NEC next time, it includes fairness, and partnering, which wiil lead to a lot more success in projects.

Regards
Philip Jonker
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Sayed, My opinions are probably close to those of Btyan. However, the question is what state of readiness (Progres in terms of mobilisation) was the contractor. Had he mobilised staff, pre project planning, was there any project related equipment purchased, how much effort was spent to prepare other than tendering (this is supposed to be carried as an overhead in normal terms) and was the contractor made aware of the possibility of cancelation of contract due to the possibility of the sale of the land. We live in different cultures, and fidics is not always suitable to the law under which it is effected. I have some experience of laws as practiced in Qatar, however, in general I believe the law is fair and will practice this fairness, in normal terms. In english law they have a term ’common law’ which refers to the way way the law is understood by most people. I believe that Islam law has simular precedents,and as such the fairness of the situation should be looked at. In other words, if the contractor accepted the contract, started mobilising, which he spent money on, and was then dropped, he is entitled to his expenses, and as a result a portion of the profits in relation to his expenses. By not taking this approaoch, and going for the cutthroat way, as dictated by the Fidics clauses, you can be doing your department irreparible damage in terms of future tenders, as the tender prices will be increased, in case more projects are abandoned, as the land prices are escalating, and the possibility is there to make more profits by cancelling further projects. The point is that if in this situation, the contractor loses money he has spent other than tendering, pay him on the basis, of the proof of expenditure, and settle the profits on the same basis, to preserve your department’s integrity. Forget the clauses an remain honest. Obviously the profit from the sale of the land was the carrot, and any good judge will see this. Regards Philip
Bryan Russell
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 14 Dec 2005
Posts: 29
Groups: None
Hi Sayed,

I’m afraid not. Profit is to be included as in my first reply, the principle is to place the Contractor back in the position he would have been had the termination not occurred. Damages in this case would be the profit that all the equipment and resources would have earnt on this job had it gone ahead, i.e. that percentage actually tendered.

The resources could have been employed elsewhere on other work, had they not been committed to your job. You might view Contractors’ equipment as a mechanism to generate revenue, including profit, to feed the company’s hungry mouths and shareholders’ pockets, whilst doing their work of excavating, etc!!
Faried Khan
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None
Thanks again Russell for your professional answer and support, only,I just wish to confirm that, in order to make sure that the Contractor will recieve fair reiembursment for the General Requirements items, in all cases he must present (by submission of evidences of vouchers, invoices, payment slips ..etc) the actual costs incurred inclusive of overhead and other charges with no profit to be considered. is that correct?
Bryan Russell
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 14 Dec 2005
Posts: 29
Groups: None
Hi Sayed,
Sub-Clause 69.3tells you that the first payment must be calculated as per 65.8, and then if the Contractor can demonstrate that he has not recovered his full expenses on any of the Preliminary and General BoQ rates, he must be paid that shortfall as damages.

The BoQ is structured with the complete job in mind and there may costs that are only recovered when completion s reached. Very much a negotiation exercise with the Contractor’s QS. The main principle is the EMployer has defaulted and the Contractor must be paid for his losses. [Plant and resources not earning for instance]

Best of luck
Faried Khan
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None
Hi Russell,

Thank you so much for your valuable response, and I would bother you further to learn more about two things which related to quantifying the claim:

- To Calculate the reimbursement for General requirements, is it as per BoQ or as per actual cost related to general requirements items, so the Contractor should submit all the relevant vouchers, invoices, ..etc to prove the claimed amount under General requirements regardless (and to forget) any rates set under BoQ for Prelims.

- If he is entitled for some compensation for termination, How to quantify such compensation?

Thanks

Bryan Russell
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 14 Dec 2005
Posts: 29
Groups: None
Sub-Clause 66.1 starts "If any circumstance outside the control of both parties .." The sale of the land cannot be classed as applicable to this Sub-Clause.
Sub_clause 69.1 (d) is suitable -"For unforeseen economic reasons it is impossible for him to continue ..."

After the notice from the Employer that the Project cannot progress, the Contractor is entitled to give notice to terminate and be paid via 69.3

Sub-Clause 69.3 tells you how to pay the Contractor, being ANY loss or damage arising out of the termination, extra over for the payments in Sub-Clause 65.8.

With regard to conflict with local law, I am uncertain of the specifics, but essentially under almost all law structures, just cancelling a contract because the Employer doesn’t want to do it anymore will normally impose severe economic payments to the Contractor. The principle is that the Contractor must be placed in the position he would have been had been able to complete the job as he had tendered, including profit.