Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Variations and Extesion Of Time

8 replies [Last post]
ashraf alawady
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
if we have a contract for excuting 10KM road and we have issued an istruction to the contractor to add another 2KM more.
is this can consider as a variation and does the contractor has the right to claim for EOT.

Please advise me

Replies

Clive Randall
User offline. Last seen 17 years 22 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
There is no doubt that adding 2km of road to a 10km project is at the least a variation
However it may be that this is not an instruction that can be issued due to its magnitude and it may be that it requires a supplementary agreement.
The reasoning behind this is that the scope has increased to a degree that makes the original contract unreasonable.

Let us say that the contractor is on the limit of his overdraft with the bank, a further 20% increase in his capital requirement would push him into a position where he could no longer fund the project.

In the alternative the extra 2km may be all balanced cantilever whereas the previous 10km were all at grade, would it be reasonable to force the contractor to build the extra 2km?

What I am trying to say here is that under the majority of contracts even those heavily bastardised the contractor usually does not have to accept a variation that is so large or different that it changes the fundamentals of the original contract.

Richard Spedding
User offline. Last seen 6 years 29 weeks ago. Offline
Joined: 20 Mar 2007
Posts: 127
Dear All

What is to stop you mobilising additional resources to complete the 20% additional work, and still finish on time?
We seem to be constrained by the resources available at the moment. Is this a reasonable constraint?
If it is reasonable / possible to obtain the additional resources, then there is a duty on the contractor to mitigate delays to the contract on the client’s behalf.
There is an entitlement to additional money for additional work, and if it can be shown to be necessary, additional time.
Siva Kumar
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 5 Jul 2005
Posts: 44
Groups: None
prabu deva
User offline. Last seen 14 years 6 weeks ago. Offline
Joined: 31 Jan 2007
Posts: 8
Groups: None
Thanks a lot hani,

Still need some clarification,is the eot to be determined based on the as planned impacted method or
time impact analysis method which considers the contractors delay also,accordingly if both the delay already caused by the contractor and the likely delay due to the V.O if both are equal,can the client deny to pay prolongation for the period of eot ,because regardless of the V.O the contractor is already delayed
Hani El Sherbini
User offline. Last seen 18 years 13 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Prabu,

you need to present to the Client/Engineer the as planned resources that was required to execute the original work scope and the associated duration based on your approve baseline schedule.
Using the same productivity rates and resource level you should be able to demostrate the time impact and the required EOT.

Now this exercise has nothing to with the contractor being delayed-Unless the dealy is caused or related to the subject VO - beacuse the contractor may accelerate his at his own expense to recover his own delays and escape liquidated damages.

Now being granted EOT you have all the right to claim for the associated costs to that time, which may and may not include pro;ongation cost.

hope that would help!!!
prabu deva
User offline. Last seen 14 years 6 weeks ago. Offline
Joined: 31 Jan 2007
Posts: 8
Groups: None
What is the appropriate method to evaluate time impacts of variations ,e.g assume quantities have increased say 20%,is as planned impacted method appropriate,or time impact analysis considering the contractors delay on the date of issue of V.O to be considered,incase of this method ,there is a contractors delay concurent with the v.o,whats the fair evaluation concurent delay EOT without prolongation cost to the contractor if contractors delay is equal to the delay caused to the impact of v.o
Shahzad Munawar
User offline. Last seen 10 years 3 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Issuance of insturction for extenion of works surely entitles you variations as well as Extension of Time.
Bijaya Bajracharya
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
This is definitely a variation. After adding 20% additional work you cannot hope to get it completed in the original time.