Prepurchase Recovery

1 reply [Last post]
Mncedisi Matiwaza
User offline. Last seen 18 years 12 weeks ago. Offline
Joined: 12 Mar 2007
Posts: 3
Groups: None
In a supply & fix contract based on the BOQ:
1. how does the client recover the amount of pre-purchase he has done?
2. is it justifiable for the contractor to claim the administration costs on escalations on the pre-purchased materials?

Thanx

Replies

Clive Randall
User offline. Last seen 17 years 24 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
1) He would generally identify those items in the bills that he was to supply and seek only a storage and installation rate. If he awards a contract and then pre purchases elemnts of materials that are in that contract he places himeself in a digfficult position and will have to issue a variation order. The valuation of the supplied materials will then be open to negotaition unless there was a breakdown of the Bof Q scheduling labour plant and materials.
2) I fail to see how the contractor could claim for admnistering the costs of escalations on materials he did not purchase