Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Liquidated Damages

9 replies [Last post]
Samagata Chakravorty
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 16
Groups: None
Hi,

can any one comment on the following,

if the contractor delays completion but no effective non-completion certificate is issued by the architect/engineer under a JCT contract,will this mean that the employer loses the right to deduct liquidated damages?



regards
Sam

Replies

ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
In UAE ,we are using the general condition of contract which almost has ben extracted from FIDIC.

we have never used JCT.
Samagata Chakravorty
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 16
Groups: None
Thax Andrew for ur valued comments.

sam
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
It does depend on what version of the JCT contract you are working on though - I’m assuming it’s 1980 or later.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Samagata,

Both the issue of a certificate and a request made in writing by the employer to deduct liquidated damages, are condition precedents to the Employer deducting liquidated damages.

A certificate of non completion can not be issued after issue of the final certificate and so if not issued before the final certificate, the employer will lose his rights to liquidated damages.
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
The client can not lost his right due to non issuance of ’no effective non-completion certificate’ .
As per the contract the only certificate which can prove that the contractor has completed the woke and maintane it properly is the maintanace certificate.

That mean even the issuance of taking over certificate can not hold the client right to deduct the liquidqted dameges at any time befre issuing maintanace certificate.
Non issuance of ’ non-completion certificate’can not consider as basis for any contractual issues .
Larry Bjorn
User offline. Last seen 11 years 25 weeks ago. Offline
Joined: 4 Feb 2004
Posts: 59
Groups: None
Sam,

Can a non-completion certificate be backdated?

Regards,
Larry
Samagata Chakravorty
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 16
Groups: None
hi akhilesh,

JCT stands for Joint Contracts Tribunal. its a Standard form of Construction Contract like FIDIC.

sam
Oliver Johnstone
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 13 Mar 2006
Posts: 5
Groups: None
Yes
Akhilesh Shukla, ...
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 13 Jul 2005
Posts: 11
Groups: GPC Qatar
Hi Sam

[English only, please - The Moderator]
Wht’s JCT contract?


Regards

Akhilesh Shukla