Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

NO CLASUE

2 replies [Last post]
Shahzad Munawar
User offline. Last seen 8 years 51 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
If there exist no clause in Contract regarding payment of material advance and Engineer redndered his decision in favour of Contractor under Clause (Engineer’s decision) but Employer refused to pay in absence of any Clause then for this claim what should be the best remedy:

Whether we opt arbitration or law suit

Replies

Anil Gupta
User offline. Last seen 16 years 7 weeks ago. Offline
Joined: 18 Aug 2003
Posts: 27
Groups: None
I think Employer has full right to know and stall the payment if Engineer(Consultant)has approve material advance without any justification to contract document. Even if u follow law suit u r gonna loose as ur contract doesn’t specify anything regaring material advance payment.
Dinesh Kumar
User offline. Last seen 5 years 51 weeks ago. Offline
Joined: 3 Jan 2004
Posts: 37
Groups: None
Hi there,

1. I presume this engineer you are refering to is the contract administrator.His certification is not final and binding and the client has the right to challenge it.

2.If there no clause in the contract allowing employer to pay for the material then you most likely have no claim so do not bring it further as it is just waste of money and time.

3.Regarding the arbitration or litigation,now a days all contracts has a arbitration clause.if that is in place you only can go for arbitration,except for order 14 cases.

Regards

Dinesh