Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

As built programme

No replies
Chris Wilson
User offline. Last seen 6 days 20 hours ago. Offline
Joined: 21 Oct 2016
Posts: 16
Groups: None

Hi,

I have a programme where I have been recording progress on a weekly basis but I have not been using it as a live programme i.e one that you reschedule on a weekly basis. I am now trying to crate an as built programme from it.

I know that If I do a reschedule at the last progress period only those activities not complete will shift and complete tasks dont shift from the baseline however I am wanting to show the progress throughout the project.

Does anyone know how to do tihs?

I was thinking I would have to go back to the first progress period and reschedule to that then the 2nd , 3rd 4th etc so activities shfted to period in wihch they were complete but not sure but this seems like a lot of work and not sure how to set reschedule options to only account for the progress at that week in the reschedule.

Any help appreciated.

Regards

Chris