asta power project

2 replies [Last post]
Tolga Taluy
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 7 Jul 2015
Posts: 9
Groups: None

Good morning All,

I am trying to establish a KPI graph based on weekly activity count of the programme to display the progress of the project.

All I can do is resource the project and and create a histogram based on all resources and export the data to excel.

But I am sure there is another way (way easier and less time consuming) to reach weekly activity counts data and export to excel. I appreciate any  feed back may help.

Regards. 

Replies

Ben Taunt
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

You could also simply run a time-slice filter...

Mike Testro
User offline. Last seen 28 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Tolgay

If you want to know the number of tasks being worked on in any given week just progress the works and then filter on work in progress.

Just add the number of tasks to your spreadsheet.

Best regards

Mike T.