demo not working

7 replies [Last post]
Rafael Davila
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
I just downloaded the demo, installed it and tried to crate my first filter, but could not even see the new filter screen, as soon as I click on new filter a dialog box displays an error. Any idea of why this error?

I want to filter activities or tasks that are out-of-sequence and also filter for lag not equal 0. I use SureTrak and can filter by lag, while P3 cannot do it. SureTrak nor P3 can filter out-of-sequence activities although both generate a report that lists those activities that are out-of-sequence. Can Powerproject do that filter?

Best regards,
Rafael

Replies

Ferdinand U.
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
hi rafael

download the file Asta_Security Patch_2009-03-03

install and restart.

it should work.

i also use demo version 10 only.
Rafael Davila
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Was an issue with two DLL files.

One was deleted and replaced when re-installed MS Project the other was cleared by right clicking the DLL, properties and selecting an option for DLL from other computer?

Well it solved the problem. Don’t ask me, Hammer Rule, if it don’t fits hit it with a Hammer until it fits!

Error from the event viewer was:

Event Type:     Error
Event Source:     Asta
Event Category:     ACCESS_EXCEPTION
Event ID:     484
Date:          7/20/2009
Time:          10:18:14 PM
User:          N/A
Computer:     RAFAEL
Description:
The thread tried to divide an integer value by an integer divisor of zero. Exception occurred at address 0x60032dfb
0x60032dfb(0) : FM20.DLL at ?
0x60071019(0) : FM20.DLL at ?
0x6008bb25(0) : FM20.DLL at ?
0x600378d3(0) : FM20.DLL at ?
0x650a1081(0) : VBE6.DLL at ?
0x6509f206(0) : VBE6.DLL at ?
0x6509ffec(0) : VBE6.DLL at ?
0x650a25c5(0) : VBE6.DLL at ?
0x650aed6d(0) : VBE6.DLL at ?
0x65099d49(0) : VBE6.DLL at ?
0x6509a10a(0) : VBE6.DLL at ?
Module: Client. Exception code: 411. File: .\source\Utilities\exception.cpp. Line: 1318.

Best regards,
Rafael
Mike Testro
User offline. Last seen 44 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Rafael

"Ialso filter for lag not equal 0. Can Powerproject do that filter?"

Sorry but PowerProject will not filter on Lead lag links.

Maybe on V 11 but I have not seen it on any development wish list.

Best regards

Mike Testro.
Rafael Davila
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Mike

I tried both advanced and beginner, even minimum install and full install.

I believe the problem is with some missing or outdated system files, some DLL’s, or perhaps the solution is using something like a pre-requisite pack some software do use like Bentley/ASA rebar, a software used by re-bar suppliers.

Let see what they come with, is just that I am somewhat eager to try the software. I cannot ask for more if not under their support agreement, which by the way is reasonable.

Best regards,
Rafael
Mike Testro
User offline. Last seen 44 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Rafael

Try going to Help > User level > Advanced

You may be in Beginner mode.

Best regards

Mike Testro
Rafael Davila
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Ferdinand.

Did not work, downloaded a non-English language patch and did not recognize it.

I am using version 10 demo, after you pay for it you can activate it, don’t know if limited under evaluation.

I e-mail asta the issue; let’s see if they come out with an answer.

The error shows a division by 0 errors and mentions a couple of DLL files followed by a question mark.

I never had installation issues with P3 nor with SureTrak, nor with Spider Project demo. The only two programs I ever had with installation issues are P6 at another contractor’s office and now Powerproject at my own PC. I am starting to believe it is as much of rubbish as P6.

Best Regards
Rafael
Ferdinand U.
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
hi rafael

try to download asta security update (Asta_Security_Update_Installer.zip) patch from asta website

http://www.astadev.de/pp_patch.0.html