Power Project to MS Project

7 replies [Last post]
Selina Logan
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 4 Apr 2001
Posts: 9
Groups: None
Can anyone advise on how to convert a pp programme into MSP? And just to make it a bit more of a challenge - I have the Asta viewer - not the PP software - can this be done without PP license?

Replies

Matthew McCombs
User offline. Last seen 7 years 35 weeks ago. Offline
Joined: 1 Nov 2017
Posts: 2
Groups: None

Does anyone know how to convert 2003 Microsoft Project Files into Asta Power project?

Ben Taunt
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Varun,

What version of Asta Powerproject are you using?  In the latest release, version 13, you can simply save your file to MS Project XML format or now also .mpp if you have MS Project installed alongside Asta Powerproject.

The help files are full of advice on any differences between how the data is converted so do take a read of those to understand the process best.

Thanks,

Ben 

 

 
varun shinde
User offline. Last seen 9 years 51 weeks ago. Offline
Joined: 15 Jul 2015
Posts: 2
Groups: None

I want to export Full loaded with Quantity & Cost ASTA PP file to MSP. It this possible to view same quantity & Cost in MSP?? If yes what is d procedure??

Shahzad Munawar
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
I totally agree with Alex that saving in XML format by using PP version 8and opening in MS project may not serve your purpose because by doing that you will lost a lot of data especially colour coding therefore it is advisable to use ASTADE macros first and then import XML file.

Andrew Pearce
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175
The other way is if you can get the originator of the PP file to send you the file exported in xml format.