Assistant Scheduler, Hyundai Engineering and Construction Co. Limited, Nuclear Power Plant

START Date: 
December, 1996
END Date: 
October, 2000

Setting up baseline schedule of each construction package

Monitoring time, resources and progress

Build up the catch up plan

Managing of interface between each construction package

Drawing of six month rolling schedule, three weeks daily schedule, as-built schedule

Preparation of Project Managers Meeting (each 2 months), Project Review Meeting (each 6 months)

Weekly meeting with clients’ schedule managing team (KEPCO)

Development of Bulk resources database using Microsoft access