Establish Management Procedure

Planning Manager, Leighton Contracting Qatar, Al Shaqab Equestrian Centre, Doha, Qatar

START Date: 
August, 2006
END Date: 
January, 2008
  • Manage a team of 4 Planning Engineers
  • Produce a project preliminary programme
  • Prepare programme management & performance management procedures
  • Develop contract programme and agree critical paths with Client / PMC
  • Develop construction Information release requirement schedule
  • Develop procurement schedule
  • Provide concise schedule and planning requirements for inclusion in bid packages
  • Evaluate nominated & domestic supplier and subcontractors’ schedule
  • Compile Monthly Progress Reports to the Client /

Planning Manager, Al Naboodah Laing O'Rourke, Burj Dubai - Old Town Commercial Island, Dubai

START Date: 
June, 2002
END Date: 
August, 2006

During Tender Stage:

  • Establish programme strategies/method of construction
  • Prepare & analyze tender programme.
  • Estimate man power and plant & machinery requirements
  • Estimate formwork / scaffolding requirement
  • Participate in final settlement meetings to put together a competitive tender

During Construction Stage:

  • Manage a team of 5 Planning Engineers and 5 Performance Measuring Engineers
  • Produce a proje

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Syndicate content