Logos Engenharia S.A. Planner

START Date: 
January, 2010
Current Role

Planner Engineer, Conduto, GASCAC Brazil - 28 inch 300Km gas pipeline

START Date: 
June, 2008
END Date: 
January, 2010

Issued and update Planning documents like:
-Dialy works report;
-WBS;
-Detail Work Schedule;
-Histograms;
-others controls;
Coordinate the department when the manager is on vacation, or license.
Control Measurement.
Grab information from another departments.
Support planning thecnicians and others departments that need planning informations.
 

SINOPEC Assistant Planner

START Date: 
June, 2006
END Date: 
May, 2008
Issued Planning documents like Monthly Report and productions follow-ups to director.
Created WBS control.
Control Measurement.
All activities working for an EPC agreement in a 300km 28” gas pipeline.

Logos Engenharia S.A. Planner

START Date: 
January, 2010
Current Role

PLANNER TECHNICIAN, Construtora Andrade Gutierrez, ANGRA 3 - NUCLEAR POWER PLANT CONSTRUCTION

START Date: 
December, 2009
END Date: 
October, 2010

Project planner:

Creater master plan baselines with labor and material resources with Primavera Solution.

Schedulling and Project Control; dates, resources and productions rates managament.

Integration between Primavera P6 with other tools.

Planner

START Date: 
December, 2009
Current Role

International Architects & Designers Planner

START Date: 
December, 2009
Current Role

Habilis GP Planner

START Date: 
December, 2009
Current Role

CH2M Hill Planner

START Date: 
November, 2009
Current Role

Constructora Norberto Odebrecht - Venezuela Planner

START Date: 
October, 2009
Current Role

Market Place