Expert Planning & Project Control Engineer, Petrochemical Industries Development Management Co. (PIDMCO), Sulfur Removal Unit, Ilam petrochemical complex

START Date: 
June, 2018

-Monitoring & Controlling time schedule and Plan with Critical Path Methodology,
-Estimating at Completion,
-Progress analysis and Monthly reporting, including histograms with Primavera P6 R8.3.
-Update Work Breakdown Structure and S-Curve diagram with Excel.
-Check and control contractor`s Invoices.